NOTE:
THE DRAWINGS SHOWN BELOW ARE A CONCEPT. FINAL SOLUTIONS OF LAND DIVISION, MATERIALS, CUBATURE SOLUTIONS, ETC., MAY BE REVISED ON A FURTHER STAGE OF THE INVESTMENT PROCESS.
THE PROJECT IS PROTECTED BY COPYRIGHT
PARAMETRES RESULTING FROM THE LOCAL AREA DEVELOPMENT PLAN RECORD FOR B_01 + B_02 SECTOR |
|
PARAMETER | RATIO |
Plot area | 100% = 16 825 m² |
Floor area and site hadscepe ratio (buildings, hard-paved area, access paths and driveways, car parks) | max. 80% = max. 13 460 m² |
Soft landscaped area | min. 20% = min. 3 365 m² |
Parking spaces as compared to: - Usable area - Number of work stations - Number of users - Transport service stations (KS) |
2-5 mp / 100 m² 2-5 mp / 10 w.s. 2-3 mp / 10 u. 2-3 mp / 1 s.s. |
Building alignment from border line with local road (KL) Building alignment from outer edges of A4 motorway |
10 m 50 m |
Maximum building height | 18 m |
INTENDED LAND USE | |
PP - production area, manufacturing, processing and technical services PS - storage and technical services area KS - transport services area UX - tundefined services area KP - carparks area EE - areas and structures of electrical power equipment |
PARAMETRES COMPATIBLE WITH GRAPHIC PROPOSAL OF LAND DEVELOPMENT FOR B_01 + B_02 SECTOR |
||
PARAMETER | AREA / NUMBER | |
AREA EQUATION |
Plot area | 16 825 m² = 100% |
Build-up area | 3 890 m² = 23% | |
Soft landscaped area | 6 406 m² = 38% | |
Paved-surface area | 6 529 m² = 39% | |
Usable area (approx. 80% of total build-up area) | 3 112 m² = 80% bua | |
Parking spaces as compared to * : - Usable area - Number of work stations - Number of users - Transport service stations (KS) |
94 mp / 3 112 m² p.u. 94 mp / 470 w.s. 94 mp / 470 u. 94 mp / 47 s.s. |
|
Building alignment from outer edges of A4 motorway | 50 m | |
Building high | 11 m | |
Cubature | 42 790 m³ |